41InRoom Controller - Operating Instructions
A5
Control
The corresponding commands:
Times are entered in seconds.
The numbered callouts refer to the corres-
ponding passages in the descriptive text.
Display
Valves
G-valve
The pressure setpoint is entered in the 2nd
line and relates to the refrigerant condensa
-
tion pressure in the condenser.
The pre-start serves to provide a sufficient
flow for the heat absorbing medium and to
pre-cool the heat absorbing medium. When
compressor operation is requested, the
G-valve opens and the compressor start is
delayed by the pre-start time.
The pre-open value is the G-valve opening
which should be obtained during the pre-
start time.
To avoid a constant discrepancy from the
set value there are three parameters, which
imitate the behavior of an integral control.
The control factor
is the decisive value, by
which the extent of the control correction is
adjusted in the way of calculating the actua
-
ting variable after the lapse of an adjustable
control cycle (0-10 sec) according to the
following formula:
S
new
= S
old
- f • (set value - actual value)
S: actuating variable - in this case, valve
opening
f: control factor
Set value: condensation pressure
To avoid a drastical change you can adjust
a maximum control correction
(0 - ±10%).
This control correction relates to the old
actuating variable in each cycle.
gvalve press 18.4
gvalve pretime 15
gvalve preopen 40
gvalve fact 2
gvalve concyc 5
gvalve maxc 5